Home›Four custom cooling coils: three cost changes, one unchanged contract price

Four custom cooling coils: three cost changes, one unchanged contract price

Four custom cooling coils left our Dezhou workshop in late October for a HVAC contractor in Suzhou, Jiangsu. The coils are used as two stacked pairs, four units in total, each with its own length, height and coil connection layout — and each one four-row, nano-coated, black.

Four custom cooling coils

What had to be built

Two groups, two coils each, stacked one above the other. Group one measures 2650×800×250 mm and 2650×1350×250 mm, left-handed, copper tube φ12.7×0.8 mm, flanged spigots DN50 and DN80. Group two measures 2300×790×250 mm and 2300×1250×250 mm, right-handed, copper tube φ15.88×0.8 mm, spigots DN65 and DN80. All four are four-row, with an overall nano coating and galvanised steel pipe connections.

Nothing here is a catalogue item. Once the outline drawing is fixed, a few millimetres on the inner frame changes air-side resistance, water volume and heat transfer, so every unit is built to its own drawing.

Drawings first, then the contract

We entered the parameters of all four units into our coil order-drawing tool, exported the outline drawings with connection positions, and sent them back for checking. Once the client confirmed, those four drawings became an inseparable annex to the manufacturing contract, with the same legal effect as the contract text. Production and final inspection both follow those four sheets.

Three cost changes, one unchanged price

The first came at drawing review: the quotation had been calculated on φ12.7 copper tube, but group two actually needs φ15.88. Thicker tube costs more and changes the circuit layout. We recalculated, absorbed the difference and kept the quoted price.

The second was a process misunderstanding. The client asked for anti-corrosion and blackening, and both sides initially assumed the “overall nano coating” written into the contract meant electrophoretic coating. Before production started we confirmed that electrophoresis and nano coating are two completely different processes, with a large price gap — and nobody in Dezhou applies nano coating, so the coils had to be sent to a subcontractor in Tianjin and brought back, with transport alone close to RMB 2,000.

Nano coated coil fins

The easy options were to ask for more money on the grounds of a misunderstanding, or to quietly switch to cheaper electrophoresis. We did neither. The contract says overall nano coating, so the coils were nano coated and the extra cost stayed with us.

The third came from the workshop: the K and I sections of the connection stubs add up to the overall length, and the drawing did not match assembly in practice. Instead of changing the drawing on our own, we filmed the workshop feedback and sent it to the client. The decision was made on the spot: inner dimensions unchanged, K shortened, I lengthened, overall length unchanged — and the client trims the excess on site when welding.

Coil side plate and header detail

Packing and delivery

Each unit went into a timber crate, with an “upright” arrow painted on the panel and the second group marked “2nd group upper” and “2nd group lower”, so the site cannot mix up positions. Freight and crating were included in the contract price. On copper wall thickness we gave the client a plain commitment: built to 0.8 mm, checked batch by batch with a calliper, and if a destructive test on any unit measures below 0.78 mm, that unit is refunded in full.

Coils in timber crates

Upright and group markings on crates

Custom coils loaded for shipment

One more thing, found before invoicing

While checking the invoice against the contract, our finance team found that the stated contract total was lower than the sum of the four unit prices — by then the contract was sealed, the goods were shipped and the client’s budget had long been approved. We told the client exactly what had happened: a transcription error in the total, not a new price increase. Two options were offered — settle at the corrected total, or keep the contract total and confirm in writing that the coating meets the contract, that goods are accepted on arrival, and that no further dispute over the coating process would follow. The client chose the second.

For custom coils we ask for the outline drawing, tube diameter, row count, connection positions and design conditions; drawings and quotation come back within one working day. Send your requirement.

Selection, quotation or technical support?
Mon–Sat 8:00–18:00 (GMT+8) · Wechat / WhatsApp available