A fan coil unit that leaks rarely leaks on the day it is installed. It leaks in the first heating season, above a ceiling, in a room where nobody is watching. That is why the pressure test is a production step here, not a final inspection we skip when we are busy.
Every coil is charged with dry nitrogen to 1.5 times its working pressure and held. A pressure drop over the hold time means a leak, and the coil goes back for repair rather than forward to assembly. Testing the coil alone is deliberate: once it is inside a casing with a fan and a drain pan, finding a small leak takes far longer.

After assembly the water circuit is pressure-tested again through the actual connection stubs, so the joints the installer will tighten are the joints we tested. Fan rotation, three-speed operation, motor current and drain pan flow are checked in the same run.
Units that arrive already pressure-tested change the site sequence: the contractor can pressure-test the whole pipe network knowing the units are not the weak point, and commissioning faults point at site work rather than at the equipment.

If you need the test record for a project, ask us for it with the unit tag numbers — it is kept against each serial number.