Once the ceiling is closed, every mistake under it costs ten times more to fix. These are the checks we ask contractors to sign off before the panels go back up.
Pipe insulation continuous and vapour-sealed, including valves and strainers. Strainer fitted with the mesh facing the right direction. Coil connections tightened with a proper seal, not thread tape alone. Air vent at the high point. Drain pan level, drain pipe on a continuous fall of at least one percent, trap fitted where the unit runs at negative pressure.

Filter in place and the correct grade. Fan rotates freely by hand and in the right direction when powered. Duct connections sealed, no collapse at the flexible joint. External static pressure measured against design, not assumed.
Access hatch positioned over the valve and filter, not just over the unit. Unit tag visible from below. Pressure test record and commissioning sheet filed with the tag number — that is what an owner will ask for in two years.

Our commissioning checklist covers all twelve; ask for it with the order and the site team can sign each line off as it is finished.